Focus: Fire-Life Safety / Column

Life Safety Q&A: Time allowed for repairs

By Brad Keyes / Special to Healthcare Facilities Today
November 15, 2017

Q:  What are the time frames for repairing life safety deficiencies found during routine inspections? How much time would be allowed to repair emergency exit signs, or failed smoke detectors?

A: Whatever is reasonable… Most AHJs will work with you on this, as long as the time-frame is reasonable. If all you need to do is install four new ‘Exit’ signs, then a month or so is reasonable. But a year would not be considered reasonable.

A failed smoke detector should not take more than a month or so, unless it is such a special item that delivery time is excessive. While I’ve never seen a set time-limit for life safety repairs, all of the AHJs I’ve worked with are willing to work with you. If you need extra time due to extenuating circumstances, they will be understanding. You may have to fill out some paperwork to have extra time, but that’s part of the business.

Brad Keyes, CHSP, is the owner of KEYES Life Safety Compliance, and his expertise is in the management of the Life Safety Program, including the Environment of Care and Emergency Management programs.

See the latest posts on our homepage


Share

Topic Area: Regulations, Codes & Standards


Recent Posts
Recent Posts

Many pediatric hospitals are including behavioral health services


Designers on behavioral healthcare projects are creating soothing environments with features a younger patient will like, according to an article on the Healthcare Design website

2/20/2018

Fake paramedic found wandering the halls of Royal Adelaide hospital


Incident represents a major security breach for the newly opened Australian hospital

2/20/2018

DebMed Offers Triclosan Alternatives Following FDA’s Healthcare Antiseptic Final Rule


2/20/2018

ePIPE® Team Awarded Two U.S. Patents for In-place Protection of Nonmetallic Pipes, Adding to Existing Portfolio of Over 30 Patents


2/20/2018

New Marley MD Everestä Counterflow Cooling Tower’s Modular Design Speeds Site Delivery and Installation


2/20/2018





Post Comment




FREE
NEWSLETTER

• News and Updates
• Webcast Alerts
• Building Technologies



All fields are required.