BIM/VDC made a complex MEP installation possible at Lurie Children's Hospital

Twenty-three stories up, the mechanical floor at the Lurie Children's Hospital in Chicago is a testament to the design and operations pressures the vertical strategy created.

By Healthcare Facilities Today


Built in a tight urban footprint, the Lurie Children's Hospital in Chicago had to go up instead of out. Rising 23 stories, the mechanical floor is a testament to the design and operations pressures such a vertical strategy created. The 12 layers of mechanical, electrical and plumbing (MEP) considerations in the 42-foot high space were made possible by a highly coordinated Building Information Modeling/Virtual Design and Construction (BIM/VDC) process, says an article in Building Design + Construction.

When the project to replace the nearby Children's Memorial Hospital began in 2005-06, using BIM and an integrated design process was far less common than it is now. And with non-repeating floor plans, the 1.25 million sq. ft., 288-bed hospital was a challenge by itself, to say nothing of the 60,000 sq. ft. 2-story mechanical floor.

By using a BIM/VDC process, the project team was able to detect clashes in systems and collaboratively resolve them in the model. "Tens of thousands of coordination issues were resolved virtually," says the article. From the 3D model, some subcontractors were able to prefabricate systems off site, improving accuracy and speed of installation.

The design team also made sure to heavily involve the operations and maintenance team, and so was able to build considerations for ease of operation into the design. For example, an access pathway safeguards access to equipment for maintenance and inspection. Due to the compressed footprint and layering of systems, however, some of the access routes are a bit tortured. One smoke damper called out in the article requires a trip up a ladder, across an air handler, getting through a 12-foot duct and then going up another ladder. 

The design team used laser scanners to create point cloud models of the MEP systems as they were installed, comparing the real-time installation to the BIM information. By doing this, necessary changes in the field were captured for the as-built drawings. 

Read the article.



May 20, 2013


Topic Area: Architecture


Recent Posts

AI Adoption on the Rise Among Leaders

AI usage increased in all markets in the fourth quarter of 2025.


TriasMD Officially Opens DISC Surgery Center at Tarzana

At 10,930 square feet, DISC Surgery Center at Tarzana includes three high-technology operating rooms and 11 patient care bays.


Goshen Health Announces Partnership with Parkview Health

Through this partnership, Goshen anticipates becoming Parkview's largest hospital outside of Fort Wayne and will serve as a regional hub for care, access and growth.


Severe Winter Weather: What Healthcare Facilities Must Prioritize

Prioritizing critical systems and strategies is key to protecting patients, staff and operations during severe winter weather.


Recovery Centers of America Opens New Facility in Florida

Spanning 19 acres, the campus will include seven buildings, a pond, an outdoor recreation area with a pool, a full basketball court and a rock-climbing wall.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.