Dealing with healthcare construction cost and schedule challenges

Henry J. Carter Specialty Hospital and Nursing Facility's shorter construction schedule forced designers and contractors to re-evaluate plans


Henry J. Carter Specialty Hospital and Nursing Facility's shorter construction schedule forced designers and contractors to re-evaluate plans, according to an article on the Healthcare Construction + Operations.

The original objective was to relocate the facility from Manhattan’s Roosevelt Island to the Harlem neighborhood.

The $285 million project would be divided into two projects: renovating 270,000 square feet of the former North General Hospital in Harlem and building 185,000 square feet of space next door to accommodate a new, 164-bed nursing facility, the article said.

A technology school was going to be built on the site where the original hospital was located and building needed to be demolished quickly. The expedited demolition date moved the completion and patient-move date for Henry J. Carter up to November 2013 and shrank the schedule by 16 months.

The solution was to regroup and implement integrated project delivery (IPD) strategies and a collocation system. 

Read the article.

 

 



January 23, 2015


Topic Area: Project Management


Recent Posts

How Efficiency Checklists Help Hospitals Save Energy, Water and Money

Keith Edgerton explains how a simple, systematic tool can help healthcare facilities identify savings, support sustainability goals and reinvest in long-term decarbonization.


What To Know Now About OSHA's Updated Hazcom Rule

The update requires careful attention because compliance is not optional, and OSHA has set firm deadlines extending through 2028.


Skills Gap Remains Wide in Facilities Management

Many candidates lack the skills that are needed to be a facilities manager.


Making Healthcare Lighting Retrofits Work

Effective operational planning determines whether a retrofit project improves a facility or creates new problems.


Harris Health to Build New Freestanding Cancer Center

The center is planned to open in 2029, following the opening of the new O'Quinn Hospital along the North Loop at Lockwood.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.