Electrical, power, lighting in stand-alone healthcare buildings

Stand-alone medical buildings and specialized treatment facilities are engineering challenges


Stand-alone medical buildings and specialized treatment facilities are engineering challenges, and more are being designed and built due to changes in healthcare requirements, according to a Q&A on the Consulting-Specifying Engineering website.

CSE asked the respondents to describe a recent electrical/power system challenge you encountered when working on a stand-alone medical building or specialized treatment facility.

With buildings typically around 10,000 sq ft, the electrical service can be relatively small, but the inclusion of imaging equipment with large in-rush demands may sometimes become an issue. Finding a balance between sizing the service appropriately for the equipment to be included, and not oversizing it for the building, is key, according to Douglas Calhoun of WSP | Parsons Brinckerhoff. 

Oftentimes, medical office buildings are not designed to accommodate imaging equipment. Time, floor space, and budget must be allocated for coordination with the utility company, space for the new equipment, and cost for the required upgrades, Craig Kos of Environmental Systems Design Inc. said.

Read the article.

 

 



June 6, 2016



Recent Posts

Extreme Weather: The Maintenance-Resilience Link

Extreme heat serves as stress test of the resilience of utility systems that provide power, cooling and life safety functions.


Encompass Health Lower Providence Opens in Pennsylvania

The 50-bed inpatient rehabilitation hospital is the company's 11th location in Pennsylvania.


Intermountain Health Acquires Fairbourne Building for Healthcare Hub and Medical Campus Conversion

Construction on the interior of the building is underway with the city and Intermountain working closely together on the campus.


Cooling Towers at NYC Health + Hospitals/Lincoln Test Positive for Legionella

Hospital among the positive tests at 10 cooling towers in South Bronx.


Prefabricated Wall Panels Accelerate UCF Lake Nona Medical Center Construction

Case study: StoPanel exterior wall systems helped Wal-Mark Contracting meet strict Florida wind-load requirements and complete 136 panels in just 11 days.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.