David Everhard, Hasenstab Architects

Cleveland Clinic designs facility to house an 80,000-pound magnet

Research facility included an MRI room, a technology and support room, control area, offices and a mock scan room

By Healthcare Facilities Today


When Cleveland Clinic added an ultra-high resolution 7T MRI scanner to its downtown Cleveland campus, transporting and installing an 80,000-pound magnet was just part of the challenge. It had to build the right facility to house such a powerful machine, according to an article of the Healthcare Design website.

Working with Hasenstab Architects of Akron, Ohio, the design-build project included constructing a 2,300-square-foot research facility that would comprise the MRI room, a technology and support room, control area, offices, and a mock scan room.

Dealing with a magnet weight that’s triple that of a typical diagnostic magnet was just one of the challenges the project faced, David Everhard, principal-in-charge, Hasenstab Architects, said in the article. The design team also had to isolate the magnet from any vibration and/or radio frequency interference  from outside sources.

To avoid problems, the team started with vibration testing at the site, which is located on an urban campus with buses and trucks running nearby. When the results couldn’t definitively tell whether vibrations would affect the magnet, the builders created a slab independent of the building foundation and on separate footings. 

“It’s kind of a standalone pedestal that the magnet sits on,” he said in the article.

Read the article and view the photo gallery.

 



October 22, 2013



Recent Posts

The HVAC Dilemma: To Repair or Replace?

Healthcare facilities that keep repairing and optimizing aging systems past their useful life spend money on a problem they cannot solve without capital investment.


Department of Veterans Affairs Signs Lease for Community-Based Outpatient Clinic in Kentucky

Construction and facility preparation are expected to be completed by the winter of 2027, and the first patient should be seen by spring 2028.


Cameron Regional Medical Center Falls Victim to Ransomware Attack

CRMC is not currently aware of any evidence to suggest that any information has been fraudulently misused.


3 Pillars of Stronger Cybersecurity in Healthcare

These strategies can help healthcare facilities stay ahead of evolving cyber threats.


Meridian Acquires Medical Office Building in Pasadena, CA

The property was acquired for approximately $13.35 million.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.