Hospital expansion showcases BIM and integrated project delivery

The new cancer center being built at the University of Massachusetts Memorial Medical Center is a good example of how to use building information modeling and virtual design and construction (BIM/VDC) to successfully deliver an integrated project.

By Healthcare Facilities Today


The new cancer center being built at the University of Massachusetts Memorial Medical Center is a good example of how to use building information modeling and virtual design and construction (BIM/VDC) to successfully deliver an integrated project, says an article in Building Design + Construction.  

The Marlborough (Mass.) Hospital Cancer Pavilion is a 14,000-square-foot addition to the hospital. It connects to the existing facility through a concrete masonry unit (CMU) shear wall, which has grouted cells and bond beams that significantly limit the ability to pass through HVAC and electrical services from the hospital to the wing. The pavilion also houses a linear accelerator for radiation oncology. It required a vault formed in rebar with 500 cubic yards of concrete forming four-foot thick walls. By using integrated project delivery tactics, the project team was able to ensure that no coring would have to take place through the vault. The team was also able to concentrate the services from twelve down to four penetrations, which could be accommodated in the pavilion's limited ceiling space.

Success on this project started with "a written, performance- and incentive-based IPD [integrated project delivery] agreement," where the architect, construction manager and several subcontractors had to achieve specific project goals in order to receive full payment, says the article.  A project manual detailed exactly how the integrated process would be communicated and executed.

Both the architect and construction manager are well versed in using 3D parametric BIM for projects, but not all of the subcontractors had the same level of experience. The team worked together to cover gaps in experience. The trades also closely worked together to sequence installation operations to navigate the tight space.

The architect says that using an IPD process allowed them to make decisions more efficiently by having everyone at the same table, and facilitated navigating state and local agency commissioning documentation requirements, says the article.

Read the article.

March 26, 2013


Topic Area: Architecture


Recent Posts

EV Charging Stations: Planning for Safety, Convenience, Expansion

Managers need to ensure patient access, coordinate with clinical operations and ensure every phase of construction supports the facility's mission.


Why Ambulatory Surgery Centers Are Turning to Dedicated HVAC Systems

Design experts from Neenan Archistruction explain how single-unit HVAC systems for each operating room enhance infection control, comfort, and resiliency.


Ground Broken on UW Health University Row Medical Center

Construction is expected to be completed by the end of 2027.


Better, More Thorough Cleaning Saves Lives

Cleanliness is the first line of defense to protect patients from killer pathogens, but many hospitals refuse to make it a priority.


Encompass Health Opens the Rehabilitation Hospital of Amarillo

The 50-bed inpatient rehabilitation hospital is now accepting patients.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.