Hospital expansion showcases BIM and integrated project delivery

The new cancer center being built at the University of Massachusetts Memorial Medical Center is a good example of how to use building information modeling and virtual design and construction (BIM/VDC) to successfully deliver an integrated project.

By Healthcare Facilities Today


The new cancer center being built at the University of Massachusetts Memorial Medical Center is a good example of how to use building information modeling and virtual design and construction (BIM/VDC) to successfully deliver an integrated project, says an article in Building Design + Construction.  

The Marlborough (Mass.) Hospital Cancer Pavilion is a 14,000-square-foot addition to the hospital. It connects to the existing facility through a concrete masonry unit (CMU) shear wall, which has grouted cells and bond beams that significantly limit the ability to pass through HVAC and electrical services from the hospital to the wing. The pavilion also houses a linear accelerator for radiation oncology. It required a vault formed in rebar with 500 cubic yards of concrete forming four-foot thick walls. By using integrated project delivery tactics, the project team was able to ensure that no coring would have to take place through the vault. The team was also able to concentrate the services from twelve down to four penetrations, which could be accommodated in the pavilion's limited ceiling space.

Success on this project started with "a written, performance- and incentive-based IPD [integrated project delivery] agreement," where the architect, construction manager and several subcontractors had to achieve specific project goals in order to receive full payment, says the article.  A project manual detailed exactly how the integrated process would be communicated and executed.

Both the architect and construction manager are well versed in using 3D parametric BIM for projects, but not all of the subcontractors had the same level of experience. The team worked together to cover gaps in experience. The trades also closely worked together to sequence installation operations to navigate the tight space.

The architect says that using an IPD process allowed them to make decisions more efficiently by having everyone at the same table, and facilitated navigating state and local agency commissioning documentation requirements, says the article.

Read the article.

March 26, 2013


Topic Area: Architecture


Recent Posts

Cleanliness in Hospitals: Clinical Priority and Community Perception

EVS managers and communities value cleanliness for complementary reasons: managers for safety and compliance, communities for trust and comfort.


Dana-Farber Receives $50M Gift for Planned Cancer Hospital

A $50 million grant from the Yawkey Foundation will support construction of Dana-Farber Cancer Institute’s planned 450,000-square-foot cancer hospital.


Clarinda Regional Health Center Reports Data Security Incident

On or around December 15, 2025, Clarinda learned that certain data within its network may have been accessed without authorization.


Gaps in Nurses' Environmental Cleaning Knowledge Grow Amid Rising EVS Pressures

Environmental cleaning is crucial in preventing HAIs, but when the responsibility falls to those outside of EVS teams, problems arise. 


Ground Broken on the Southern Nevada Forensic Facility

Construction on the new secure forensic psychiatric hospital is expected to be completed in 2029.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.