Life Safety Q&A: Four-inch corridor projection

Brad Keyes continues the discussion on regulations for med-room corridor doors

By Brad Keyes / Special to Healthcare Facilities Today


Q: With the adoption of the new 2012 Life Safety Code by CMS, we had a discussion about projections from the corridor wall. Since the LSC only allows projections to be 4 inches, the question that came up was in regards to fire extinguishers mounted to the wall and not recessed as they project out from the wall about 7 inches. Will we be required to recess them or will they be allowed? The same question was raised about wall mounted telephones?

A: Actually, the 2012 LSC allows a 6-inch projection into the corridor [see 19.2.3.4(4)], but CMS’ Final Rule published April 4, 2016 said they will enforce the more restrictive 4-inch maximum projection into the corridor, based on the Americans with Disabilities Act (ADA). For all healthcare facilities that receive Medicare & Medicaid funds, they must comply with CMS’ exception to the 2012 LSC.  

To answer your question, there are no exceptions to the 4-inch maximum projection rule. So, anything projecting more than 4 inches into the corridor, including fire extinguishers and telephones, would likely be cited by a surveyor or inspector. 

Brad Keyes, CHSP, is the owner of KEYES Life Safety Compliance, and his expertise is in the management of the Life Safety Program, including the Environment of Care and Emergency Management programs.

 

 



August 2, 2017


Topic Area: Regulations, Codes & Standards


Recent Posts

CRAB Alert: The EVS Role in Preventing Infection

CRAB is a Gram-negative bacterium that causes bloodstream infections, ventilator-associated pneumonia, surgical wound infections and meningitis in hospitalized patients.


Why Hospital Waiting Rooms Aren't Going Away

Despite advances in technology, thoughtfully designed reception spaces continue to evolve.


Ground Broken on Mount Sinai Tisch Cancer Hospital

The hospital is aiming to open in 2030 on Mount Sinai’s Upper East Side campus.


Design, Compartmentation, Training: How Defend-in-Place Strategies Can Protect Patients

Effective defend-in-place strategies depend on compartmentation, fire-rated assemblies and ongoing staff training to protect patients who cannot quickly evacuate.


Milestone Marked with Topping Out Ceremony for BayCare Hospital Manatee

Construction remains on schedule, with crews continuing work on interior spaces, infrastructure and clinical areas throughout the facility.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.