Focus: Fire-Life Safety / Column

Life Safety Q&A: Four-inch corridor projection

Brad Keyes continues the discussion on regulations for med-room corridor doors

By Brad Keyes / Special to Healthcare Facilities Today


Q: With the adoption of the new 2012 Life Safety Code by CMS, we had a discussion about projections from the corridor wall. Since the LSC only allows projections to be 4 inches, the question that came up was in regards to fire extinguishers mounted to the wall and not recessed as they project out from the wall about 7 inches. Will we be required to recess them or will they be allowed? The same question was raised about wall mounted telephones?

A: Actually, the 2012 LSC allows a 6-inch projection into the corridor [see 19.2.3.4(4)], but CMS’ Final Rule published April 4, 2016 said they will enforce the more restrictive 4-inch maximum projection into the corridor, based on the Americans with Disabilities Act (ADA). For all healthcare facilities that receive Medicare & Medicaid funds, they must comply with CMS’ exception to the 2012 LSC.  

To answer your question, there are no exceptions to the 4-inch maximum projection rule. So, anything projecting more than 4 inches into the corridor, including fire extinguishers and telephones, would likely be cited by a surveyor or inspector. 

Brad Keyes, CHSP, is the owner of KEYES Life Safety Compliance, and his expertise is in the management of the Life Safety Program, including the Environment of Care and Emergency Management programs.

 

 



August 2, 2017


Topic Area: Regulations, Codes & Standards


Recent Posts

Inside One of Healthcare's Most Ambitious Hospital Projects 

When someone faces a serious medical condition, having access to world-class care close to home can make all the difference. 


Turning Condensate Loss into a Systemwide Steam Efficiency Opportunity

Case study: How APM Steam helped Atrium Health Cabarrus uncover hidden steam system inefficiencies and build an actionable repair plan with a projected $144,949 in annual energy savings.


The Leapfrog Group Publishes 2026 Ratings for Hospitals and ASCs

This year totaled more than 6,000 facilities nationwide.


Going Solar with No Upfront Costs

300 kW solar system and roof upgrade delivered with no upfront cost for medical center association.


Northwell Health Finds Energy Savings in Steam Systems

Case study: A proactive steam trap maintenance program is delivering millions in savings, fast payback and measurable carbon reductions across one of the nation’s largest health systems.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.