Life Safety Q&A: Quarterly test of main drain

Brad Keyes discusses quarterly testing of the main drain

By Brad Keyes / Special to Healthcare Facilities Today


Q: Has the frequency for the main drain testing changed from annually to quarterly?

A: Yes… but not for all the main drain test locations. The new 2012 LSC now references the 2011 edition of NFPA 25, and section 13.2.5.1 of NFPA 25-2011 requires once per quarter, one (not all) main drain test must be conducted on a system riser located downstream of the backflow preventer when the sole water supply is through a backflow preventer. This test must record the static water pressure, the residual water pressure, and the time required to restore water pressure to static pressure. This test is conducted with the fire pump off (if so equipped) and the jockey pump on.

You still must conduct an annual main drain test on all of the system risers.

Brad Keyes, CHSP, is the owner of KEYES Life Safety Compliance, and his expertise is in the management of the Life Safety Program, including the Environment of Care and Emergency Management programs.

 



December 6, 2017


Topic Area: Regulations, Codes & Standards


Recent Posts

How Efficiency Checklists Help Hospitals Save Energy, Water and Money

Keith Edgerton explains how a simple, systematic tool can help healthcare facilities identify savings, support sustainability goals and reinvest in long-term decarbonization.


Designing with Heart: Seen Health Center Blends Cultural Warmth and Clinical Care

Case study: The Alhambra-based facility uses Wilsonart Woodgrains to create a space where comfort, tradition and durability come together for an elevated senior care experience.


Rutgers Health and University Hospital Breaks Ground on Campus Expansion

The groundbreaking follows the long-awaited demolition of administrative offices built in the 1970s.


What to Consider When Modernizing Healthcare Facilities

While there has been a call to preserve old buildings, healthcare facilities need to weigh the options of patient care.


Corewell Health Beaumont Troy Hospital to Build New Tower

The tower is expected to be completed in 2030.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.