Q: We are planning to update a pair of fire-rated automatic corridor doors which happened to be located in our Emergency Room and in a 2-hour rated wall. The work cannot be done in one day. Besides the sensitive location, there is work to be done to reinforce the existing drywall partition, since the new doors are heavier. There are existing sprinklers on one side of the existing doors. Also, above the ceiling are existing ducts, medical gases and cabling that restricts me from installing a temporary rated partition up to the ceiling slab. Based on my criteria, what options do I have with setting up a temporary barrier before I can replace the doors? 

A: Well… you said the work cannot be done in one day. If the existing sprinkler in the construction area can remain in service without any impairments, then I don’t see a problem with putting up temporary construction barriers between the floor and the ceiling, as long as they are made with flame retardant plastic sheeting. You will need to assess it for ILSM and with the temporary construction barriers in place that would constitute a blocked exit. Most ILSM assessments for a blocked exit would require one additional fire drill in the area, but if you can get everything done in 2 – 3 days, you may not have to do the extra fire drill. I don’t see a need to do a Fire Watch as long as the sprinkler is not impaired.

If the sprinkler is impaired then a Fire Watch may be needed, based on what your ILSM policy says. Some ILSM policies do not require a Fire Watch until a branch of the sprinkler system is impaired. If the construction area is not protected with sprinklers, then technically you would need to build 1-hour fire rated barriers that extend from the floor to the deck above. But that could take 2 – 3 days to build; if you can get the door replacement project completed within that time-frame, then I don’t see the need to build 1-hour fire rated barriers… But that’s me. Some other surveyor may disagree.

Brad Keyes, CHSP, is the owner of KEYES Life Safety Compliance, and his expertise is in the management of the Life Safety Program, including the Environment of Care and Emergency Management programs.

 



January 11, 2017


Topic Area: Regulations, Codes & Standards


Recent Posts

What Does Light Daily Cleaning Miss in Patient Rooms?

Most environmental services workers still clean as if they are wiping dust off a countertop, not disrupting a living, structured community.


Smart Lighting Overhaul Boosts Efficiency, Diagnostics and Wellness at Bryan Health

Case study: LED upgrade and advanced controls across Bryan Health campuses cut lighting energy use by 57 percent while enhancing patient care and staff productivity.


AdventHealth Opens New Freestanding ER in Florida

The approximately 13,700-square-foot emergency room features 12 patient rooms, respiratory therapy services, diagnostic imaging including CT scans, X-ray and ultrasound.


Dirty Floors: How Pathogens Can Accumulate and Spread Underfoot

Studies show that healthcare floors are covered in bacteria and can quickly spread throughout patient rooms. 


WellSpan Health Opens Its Newberry Hospital in Pennsylvania

This marks the opening of its 10th hospital in the region spanning Central Pennsylvania and Northern Maryland.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.