Focus: Fire-Life Safety / Column

Regulations, Codes & Standards Q&A: Electrical room

Brad Keyes discusses regulations for electrical rooms

By Brad Keyes / Special to Healthcare Facilities Today


Q: I am aware that there is an exception for sprinklers not to be required in a dedicated electrical room that is protected with 2-hour construction. My question: Is a communications equipment room (IT and telecom wire racks and routers) also excepted from being sprinklered? The hospital’s engineer marked the communications rooms as not required in their sprinkler drawings.

A: According to NFPA 13-2010, section 8.15.10.3, sprinklers shall not be required in electrical equipment rooms where all of the following conditions are met:

1) The room is dedicated to electrical equipment only.

2) Only dry-type electrical equipment is used.

3) Equipment is installed in a 2-hour fire-rated enclosure including protection for penetrations.

4) No combustible storage is permitted to be stored in the room.

Is the room where the IT routers are housed a 2-hour fire-rated room?

Is the room where the IT routers are housed dedicated to electrical equipment only?

Is the room where the IT routers are housed free from any combustible storage?

I think you could make the argument that a IT Router room is an electrical equipment room, but does it meet all of the other requirement for sprinklers to be excluded?

Brad Keyes, CHSP, is the owner of KEYES Life Safety Compliance, and his expertise is in the management of the Life Safety Program, including the Environment of Care and Emergency Management programs.

 



December 11, 2019


Topic Area: Regulations, Codes & Standards


Recent Posts

Extreme Weather: The Maintenance-Resilience Link

Extreme heat serves as stress test of the resilience of utility systems that provide power, cooling and life safety functions.


Encompass Health Lower Providence Opens in Pennsylvania

The 50-bed inpatient rehabilitation hospital is the company's 11th location in Pennsylvania.


Intermountain Health Acquires Fairbourne Building for Healthcare Hub and Medical Campus Conversion

Construction on the interior of the building is underway with the city and Intermountain working closely together on the campus.


Cooling Towers at NYC Health + Hospitals/Lincoln Test Positive for Legionella

Hospital among the positive tests at 10 cooling towers in South Bronx.


Prefabricated Wall Panels Accelerate UCF Lake Nona Medical Center Construction

Case study: StoPanel exterior wall systems helped Wal-Mark Contracting meet strict Florida wind-load requirements and complete 136 panels in just 11 days.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.