Time-lapse Video Captures Massive Concrete Pour for New South Bay Hospital


Time-lapse video captured nearly 500 cement trucks as they filed onto the Sharp Chula Vista Medical Center campus overnight on Saturday, July 29, to pour the base of Sharp HealthCare’s newest hospital, set to open in fall 2019.

Beginning Friday night, 4,700 yards of concrete covering 25,000 square feet had been poured by the end of the 12-hour project that finished on Saturday afternoon. More than 125 construction workers, in addition to the hundreds of ready mix concrete truck drivers, were on-site throughout the night; more than 90 percent of labor for the project is local (San Diego County).

“With everything we’ve done as part of this project, we’ve carefully considered the needs of patients, their families and friends, and the community,” said David Bruce, superintendent, Hensel Phelps Construction, the general contractor for the project. “Our intent in doing this overnight was to minimize traffic impacts to the hospital and community.”

The concrete pour marks the most recent milestone – and almost halfway point – for the South Bay’s first new hospital in more than 40 years (the last new hospital was the existing hospital at Sharp Chula Vista, which opened in 1975). Sharp Chula Vista broke ground on the $244 million hospital in November 2016; once open, it will add 138 large, private patient rooms; six operating rooms; a rooftop café and more to meet the needs of San Diego’s South County region – one of the fastest-growing in the nation. The project is Sharp’s largest single investment to date and is being funded through philanthropic donations to Sharp HealthCare Foundation, bonds, cash reserves and the Medi-Cal Hospital Fee Program.



August 1, 2017


Topic Area: Press Release


Recent Posts

Gaps in Nurses' Environmental Cleaning Knowledge Grow Amid Rising EVS Pressures

Environmental cleaning is crucial in preventing HAIs, but when the responsibility falls to those outside of EVS teams, problems arise. 


Ground Broken on the Southern Nevada Forensic Facility

Construction on the new secure forensic psychiatric hospital is expected to be completed in 2029.


Jackson Hospital Falls Victim to Third-Party Cybersecurity Incident

Jackson Hospital has no evidence that any personal information has been or will be used for identity theft as a direct result of this incident.


Making Healthcare Lighting Retrofits Work

Effective operational planning determines whether a retrofit project improves a facility or creates new problems.


Stadium Design is Reshaping Healthcare Facilities

Hospitals are turning to the sports industry for innovative ways to support healing and improve the patient experience.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.