Tarlton Serving as Construction Manager on $12 Million Webster University Parking Garage Expansion


Tarlton Corp., a St. Louis-based general contracting and construction management firm, is serving as construction manager on the $12 million expansion of the Garden Avenue Parking Garage at Webster University.    

When completed in spring 2017, the 523,450-square-foot structure at 580 Garden Ave. will more than double the existing number of spaces in the garage and significantly boost Webster’s parking inventory on campus. The five-level precast concrete structure features thin-set brick, a drilled pier foundation and retaining walls, with Tarlton self-performing the structural concrete work.

The team is carrying out intensive construction while keeping the adjoining garage fully functional, with some areas closed intermittently during construction activities. Work includes deep excavation of more than 20 feet, with some drilled piers 38 feet deep. Precast concrete erection began in November, and interior work is scheduled to begin at the end of the year.

The commitment to safety is a critical component of the project. The team is navigating a mobile crane around overhead power lines and working in a tight staging area on an active college campus with high pedestrian and vehicular traffic. A high school campus is adjacent to the site and an active railroad line is within 100 feet of the building footprint.

“The Webster University Garden Avenue Parking Garage builds on our success as one of the region’s top construction managers and concrete experts,” said Tracy Hart, president, Tarlton Corp. “We are delighted to work on a project that will have such a positive impact on the Webster community.”

A live video feed of the garage expansion project can be found online at https://www.truelook.com/tl/app/?u=tw1469540660#tl_live.

The Tarlton construction management team includes Joe Scarfino, project director; Diane Grimsley, project manager; Alex Brown, project engineer; and Bill Foster, project superintendent. KWK Architects is project architect, with Walker Parking Consultants serving as structural engineer. Additional team members include Grimes Consulting, civil engineer; Webb Engineering Services, mechanical, electrical, plumbing and fire protection; and SWT Design, landscape architect.

Many Tarlton projects have been recognized for excellence in concrete work, including the first section of the MetroLink Cross County Extension, the Saint Louis Art Museum Expansion and the Mechanical Dynamics & Analysis High Speed Balance Facility, all winners of Quality Concrete Awards from the Concrete Council of St. Louis. In addition, Tarlton Vice President Steve Cronin was inducted in 2016 into the council’s Concrete Hall of Fame.  

 

 



January 3, 2017


Topic Area: Press Release


Recent Posts

Case Study: How NYU Langone Rebuilt for Resilience After Superstorm Sandy

Although the damage was severe, it provided a valuable opportunity for NYU Langone to assess structural vulnerabilities and increase facility resilience.


Frederick Health Hospital Faces 5 Lawsuits Following Ransomware Attack

The lawsuits accuse FHH of inadequate cybersecurity, poor breach notification and failing to protect patients from identity theft risks.


Arkansas Methodist Medical Center and Baptist Memorial Health Care to Merge

They have signed a non-binding letter of intent to complete a shared mission agreement to merge the two organizations.


Ground Broken on Intermountain Saratoga Springs Multi-Specialty Clinic

The clinic is scheduled to open and start seeing patients in the fall of 2026.


Electrical Fire Tests Resilience of Massachusetts Hospital

Signature Healthcare Brockton Hospital used opportunity to renovate key systems and components and expand facility operations.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.