Caldwell Adjustable Spreader Beam Lifts Rothera Wharf Frames in Antarctica


 

U.S.-based The Caldwell Group Inc. has customized an adjustable, 101,413-lb. (46t) capacity lifting beam for the latest phase of the wharf modernization at British Antarctic Survey’s Rothera Research Station. Caldwell specifically designed and manufactured the lifting system to suit the harsh, cold environment.

 

The model 24S-46t-315 adjustable bail lifting beam was delivered by Caldwell’s UK-based partner, Bishop Lifting, to BAM, who is working in partnership with the British Antarctic Survey (BAS), part of the Natural Environment Research Council (NERC), to deliver civil projects associated with the new RRS Sir David Attenborough, a research vessel owned by NERC and operated by BAS for scientific research and logistics projects. Principally, a new wharf will provide safe berthing and efficient operations for the iconic ship.

 

The 8,217mm (27ft.)-long beam was designed by Dan Mongan, special application support, new product development specialist at Caldwell. Due to the cold weather in the Antarctic, steel alloy selection, welding processes, and type of paint were all important considerations at the outset, he said. The beam was based on the standard model 24 adjustable bail lifting system, but offered higher capacity. ‘Bail’ refers to the center item that the crane hook attaches to.

 

It was 1,372mm (4.5 ft.) wide, 1,920mm (6.3 ft.) high and weighed in at 10,100 lbs. (4.58t). It was provided along with two patented model 52-58 adjust-a-leg wire rope slings with 6,705mm (22 ft.) reach. The rig will eventually be used to lift 20 wharf frames, the lightest weighing 77,162 lbs. (35t).

 

Ben Gates, business development director at Bishop Lifting Equipment, said: “The challenge was, in simple terms, to lift heavy loads, each with different centers of gravity. The adjustable bail solved the problem in that it can be adjusted in one direction and the adjust-a-leg slings in the other.”

 

Mongan said: “The successful utilization of the product on such a marquee project showcases our ability to engineer and ship below-the-hook solutions globally. Further, it serves as an example of what Caldwell and Bishop can achieve together; this project involved an extensive design phase, multiple Skype calls, and a collaboration of all relevant parties to arrive at the eventual rigging solution.”

 

As an aside, Mongan explained that adjust-a-leg slings can be locked into place for constant lifts and are ideal for use in rigging applications and machinery moving. They are often used, he said, for loads that are balanced and symmetrical, but with lifting points not located in a position for a level lift. They are also suited for use when lifting loads at any desired angle, simply by lifting the with sling legs at that desired angle.

 

Over the next decade, British Antarctic Survey’s Research Stations will undergo a comprehensive modernization program to ensure that facilities continue to enable world-leading research. 

 

The new wharf is scheduled to be built over two Antarctic seasons, starting in November 2018 and completing in spring 2020, in order to improve ship and boating operations. The rear section of the new wharf was constructed in the first season, then the front section attached during the latest phase.

 

Gates added: “This is a very interesting project. At Bishop Lifting we have been delighted to play a part—albeit a small one.”



January 23, 2020


Topic Area: Press Release


Recent Posts

Upward Mobility: Market Forces Drive Hospitals Higher

Healthcare facilities nationwide are navigating challenges and opportunities presented by expanding their reach into the sky.


Georgia Hospital Bomb Hoaxes Highlight Need for Healthcare–Police Partnerships

Proactive planning and close collaboration with law enforcement help healthcare facilities maintain safety and continuity during false threats.


MUSC Health Celebrates Groundbreaking for Nexton Hospital and Ambulatory Cancer Facility

The Nexton cancer facility is expected to open in summer 2027, and the Nexton hospital in summer 2028.


Mattresses Require Strict Care to Prevent Spread of Infections

Poor cleaning and disinfection techniques contribute to the persistent contamination of patient mattresses.


Gardner Health Services Opens Alum Rock Health Center

The 10,080-square-foot facility provides essential medical, dental, mental and chiropractic services to the Mayfair and East San José neighborhoods.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.