Closing the gap between building performance and code requirements with commissioning

Article looks at gaps between commissioning best practices and minimum code requirements for new facilities


Building commissioning requirements for commercial buildings are slowly being accepted throughout the country but it is excluded from the mandatory requirements in some states, such as California, according to an article on the Medical Construction & Design website.

The article looks at gaps between commissioning best practices and minimum code requirements for new facilities.

The American Society for Healthcare Engineering released the Healthcare Facility Commissioning Guidelines in 2010, which follows general commissioning best practices but includes some specific requirements for healthcare facilities. 

The systems covered within ASHE’s guidelines include: building envelope, life safety, HVAC systems, controls, plumbing systems, medical gas and other specialty systems, electrical systems, fire alarm systems, information technology, fire protection systems, interior and exterior lighting, refrigeration, vertical transport and materials and pharmaceutical handling. 

Read the article.

 

 



August 8, 2016


Topic Area: Regulations, Codes & Standards


Recent Posts

Extreme Weather: The Maintenance-Resilience Link

Extreme heat serves as stress test of the resilience of utility systems that provide power, cooling and life safety functions.


Encompass Health Lower Providence Opens in Pennsylvania

The 50-bed inpatient rehabilitation hospital is the company's 11th location in Pennsylvania.


Intermountain Health Acquires Fairbourne Building for Healthcare Hub and Medical Campus Conversion

Construction on the interior of the building is underway with the city and Intermountain working closely together on the campus.


Cooling Towers at NYC Health + Hospitals/Lincoln Test Positive for Legionella

Hospital among the positive tests at 10 cooling towers in South Bronx.


Prefabricated Wall Panels Accelerate UCF Lake Nona Medical Center Construction

Case study: StoPanel exterior wall systems helped Wal-Mark Contracting meet strict Florida wind-load requirements and complete 136 panels in just 11 days.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.