Connecting the new and existing systems in new central utility plant (CUP) for the Falls Church, Va., Inova Women’s Hospital and Inova Children’s Hospital created a challenge for the project team, according to an article on the FacilityCare website.
Along with an 11-story medical/surgical tower that opened in January 2013, renovations to the existing medical/surgical tower, a 10-story replacement tower for Inova Women’s Hospital and Inova Children’s Hospital, a new parking garage, and improved campus access, the Inova project included a $35 million, 17,000-square-foot CUP.
The relocation of the original generator required a disassembly and testing process that took approximately six to eight weeks.
While reconfiguring and tying the original generator into the new system was challenging, integrating it into a section of the existing hospital was even more difficult.
Mature Dry Surface Biofilm Presents a Problem for Candida Auris
Sutter Health's Arden Care Center Officially Opens
Insight Hospital and Medical Center Falls to Data Breach
The High Cost of Healthcare Violence
EVS Teams Can Improve Patient Experience in Emergency Departments