Connecting the new and existing systems in new central utility plant (CUP) for the Falls Church, Va., Inova Women’s Hospital and Inova Children’s Hospital created a challenge for the project team, according to an article on the FacilityCare website.
Along with an 11-story medical/surgical tower that opened in January 2013, renovations to the existing medical/surgical tower, a 10-story replacement tower for Inova Women’s Hospital and Inova Children’s Hospital, a new parking garage, and improved campus access, the Inova project included a $35 million, 17,000-square-foot CUP.
The relocation of the original generator required a disassembly and testing process that took approximately six to eight weeks.
While reconfiguring and tying the original generator into the new system was challenging, integrating it into a section of the existing hospital was even more difficult.
Grounding Healthcare Spaces in Hospitality Principles
UC Davis Health Selects Rudolph and Sletten for Central Utility Plant Expansion
Cape Cod Healthcare Opens Upper 2 Floors of Edwin Barbey Patient Care Pavilion
Building Sustainable Healthcare for an Aging Population
Froedtert ThedaCare Announces Opening of ThedaCare Medical Center-Oshkosh