A project architect is blaming pressure to meet deadlines and “seriously flawed” designs for a six-month delay to the opening of the Royal Hospital for Sick Children in Edinburgh, according to an article on the Scottish Construction Now website.
The architect claimed that construction of the £150 million hospital was rushed despite repeated warnings of potential design problems.
He said columns blocking the middle of rooms, lack of daylight and difficulties of trying to use the central atrium as a dual purpose outpatients’ waiting room and exhibition space with patients’ cinema were among the flaws.
NHS Lothian confirmed the hospital will not open as originally scheduled due to “unavoidable technical construction problems," poor weather and financial problems affecting two of the contractors.
Spaces That Support: Patient-Centered Design for Modern Reproductive Health
Modernization of Buildings Require Collaboration Across All Disciplines
Children's Health Announces Plans for RedBird Specialty Center in Texas
How Can Healthcare Facilities Use Efficiency to Drive Climate and Health Goals?
El Camino Health Rehabilitation Hospital Officially Tops Out