Emory University Hospital had 72 hours to ready isolation unit for 2014 Ebola patients

U.S. State Department told authorities at Emory to prepare for the arrival of the first of two U.S. Ebola patients


When the U.S. State Department told authorities at Emory University Hospital to prepare for the arrival of the first of two U.S. Ebola patients in August of 2014, the facility had 72 hours to ready isolation unit, according to an article on the Marquette Magazine.

Emory’s isolation unit was built 10 years ago in collaboration with the Centers for Disease Control and includes two ICU-style patient rooms with contained bathrooms, locker rooms where medical staff can dress in the required protective clothing and take emergency decontamination showers, and dedicated laboratory space. 

The unit is self-contained so no virus particles are disseminated beyond its confines. 

After the 2014 call, Emory staff tested and re-tested all of the systems built into the biocontainment unit. It became apparent that the unit was not large enough to accommodate the laboratory needs of two patients.  Within 72 hours they commandeered an office next door to the unit and retrofitted it with a biosafety cabinet and functioning point-of-care lab.

Read the article.

 

 



January 27, 2016


Topic Area: Industry News


Recent Posts

Cleanliness in Hospitals: Clinical Priority and Community Perception

EVS managers and communities value cleanliness for complementary reasons: managers for safety and compliance, communities for trust and comfort.


Dana-Farber Receives $50M Gift for Planned Cancer Hospital

A $50 million grant from the Yawkey Foundation will support construction of Dana-Farber Cancer Institute’s planned 450,000-square-foot cancer hospital.


Clarinda Regional Health Center Reports Data Security Incident

On or around December 15, 2025, Clarinda learned that certain data within its network may have been accessed without authorization.


Gaps in Nurses' Environmental Cleaning Knowledge Grow Amid Rising EVS Pressures

Environmental cleaning is crucial in preventing HAIs, but when the responsibility falls to those outside of EVS teams, problems arise. 


Ground Broken on the Southern Nevada Forensic Facility

Construction on the new secure forensic psychiatric hospital is expected to be completed in 2029.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.