Focus: Plumbing

Planning plumbing systems in healthcare facilities

With planning, managers can ensures the success of maintenance and upgrades of plumbing systems


One of the major challenges in planning plumbing retrofits in healthcare facilities is the impact of waste system changes on the floor below the project, which often require removing or relocating people and scheduling difficult phasing work to minimize disruption, according to an article from Building Operating Management on the FacilitiesNet website.

Hospital departments and functions often think of adjacency horizontally, not vertically. Smarter waste systems, such as vacuum waste systems, can eliminate the need for vertical planning. These systems limit renovation-related departmental disruptions, so their use in master planning can reduce renovation costs.

A similar rationale applies to planning redundancy in plumbing systems. Pumps, air compressors, and vacuum pumps require frequent maintenance and replacement, so when designers compartmentalize these systems for component replacement and provide separate power sources, the result is greater resiliency.

Also critical to successful master planning for plumbing system maintenance is the presence of service valves. Codes often do not require these valves, which become critical for future implementation and maintenance changes. They also serve a vital function for emergency shutoff during breaks or temporary issues with the plumbing systems.

Read the article.



April 22, 2020


Topic Area: Maintenance and Operations


Recent Posts

Extreme Weather: The Maintenance-Resilience Link

Extreme heat serves as stress test of the resilience of utility systems that provide power, cooling and life safety functions.


Encompass Health Lower Providence Opens in Pennsylvania

The 50-bed inpatient rehabilitation hospital is the company's 11th location in Pennsylvania.


Intermountain Health Acquires Fairbourne Building for Healthcare Hub and Medical Campus Conversion

Construction on the interior of the building is underway with the city and Intermountain working closely together on the campus.


Cooling Towers at NYC Health + Hospitals/Lincoln Test Positive for Legionella

Hospital among the positive tests at 10 cooling towers in South Bronx.


Prefabricated Wall Panels Accelerate UCF Lake Nona Medical Center Construction

Case study: StoPanel exterior wall systems helped Wal-Mark Contracting meet strict Florida wind-load requirements and complete 136 panels in just 11 days.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.