Q&A: Two releasing devices for doors

Brad Keyes says two releasing devices on doors is permitted in very limited situations

By Brad Keyes / Special to Healthcare Facilities Today


Q: I heard in a webinar that under the 2012 edition of the Life Safety Code, I can you have two releasing devices on doors. Is this true?

A: Yes, it is true, but only in very limited situations is it permitted. A new section (7.2.1.5.10.6) of the 2012 Life Safety Code allows two releasing operations to be permitted for existing hardware on a door serving an occupant load not exceeding three persons, provided the releasing mechanisms do not require simultaneous operations. This only applies to existing conditions, and does not allow you to install deadbolt locks on doors that only serve three people. Existing means the second releasing device (i.e. deadbolt lock) was on the door prior to July 5, 2016.

Brad Keyes, CHSP, is the owner of KEYES Life Safety Compliance, and his expertise is in the management of the Life Safety Program, including the Environment of Care and Emergency Management programs

 

 



July 20, 2016


Topic Area: Regulations, Codes & Standards


Recent Posts

What 'Light' Daily Cleaning of Patient Rooms Misses

Most environmental services workers still clean as if they were wiping dust off a countertop, not disrupting a living, structured community.


Sprinkler Compliance: Navigating Code Mandates, Renovation Triggers and Patient Safety

As CMS deadlines approach and renovation projects accelerate, healthcare facility managers must understand how NFPA 101, state fire codes and sprinkler design strategies intersect.


MUSC Board of Trustees Approves $1.1B South Carolina Cancer Hospital

Research and education are intentionally embedded in the hospital’s design, with dedicated spaces for scientific collaboration, clinical investigation and training.


Study Outlines Hand Hygiene Guidelines for EVS Staff

Researchers find that current guidelines for hand hygiene don’t include EVS workers and suggest indicators to fill that gap.


McCarthy Completes $65M Sharp Rees-Stealy Kearny Mesa MOB Modernization

The completed tenant improvement includes approximately 100,000 square feet of improved space across two buildings and represents an investment of $65 million.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.