Q&A on egress lighting and battery powered emergency lights

In a recent Q&A on the FacilityCare website, consultant Brad Keyes answered a question about egress lighting and battery powered emergency lights


In a recent Q&A on the FacilityCare website, consultant Brad Keyes answered a question about  egress lighting and battery powered emergency lights.

Q: The egress lighting in our facility is connected to our generator through the life safety circuit and the light fixtures have no batteries. The task lighting in our operating rooms, the generator room and the transfer switch room do have battery powered emergency lights. Is task lighting in the operating room considered egress lighting? Does the monthly testing requirement for egress lighting still apply? Does the Life Safety Code (LSC) have an exception for egress lighting that is connected to the emergency generator?

A: To start, the LSC says all required emergency lighting systems are to be tested at 30-day intervals for not less than 30 seconds (see section 7.9.3 of the 2000 LSC). In addition, this section says every required battery-powered emergency lighting system must be tested annually for 90 minutes. Egress lighting without battery back-up that is connected to the life safety branch of the EESS emergency power circuits receives the monthly test when the generators are load tested and the ATS are transferred on a monthly basis. Since the EESS generator system is not a battery back-up system, then it does not have to have a 90-minute annual test.

Read the full answer. 

 

 

 



April 21, 2015


Topic Area: Safety


Recent Posts

Cleanliness in Hospitals: Clinical Priority and Community Perception

EVS managers and communities value cleanliness for complementary reasons: managers for safety and compliance, communities for trust and comfort.


Dana-Farber Receives $50M Gift for Planned Cancer Hospital

A $50 million grant from the Yawkey Foundation will support construction of Dana-Farber Cancer Institute’s planned 450,000-square-foot cancer hospital.


Clarinda Regional Health Center Reports Data Security Incident

On or around December 15, 2025, Clarinda learned that certain data within its network may have been accessed without authorization.


Gaps in Nurses' Environmental Cleaning Knowledge Grow Amid Rising EVS Pressures

Environmental cleaning is crucial in preventing HAIs, but when the responsibility falls to those outside of EVS teams, problems arise. 


Ground Broken on the Southern Nevada Forensic Facility

Construction on the new secure forensic psychiatric hospital is expected to be completed in 2029.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.