Q&A on fire-rated barriers vs. smoke compartment barriers

In a recent Q&A on the FacilityCare website, consultant Brad Keyes answered a question on fire-rated barriers vs. smoke compartment barriers


In a recent Q&A on the FacilityCare website, consultant Brad Keyes answered a question about fire-rated barriers vs. smoke compartment barriers.

Q:  Are doors in fire-rated barriers also required to be listed and installed as smoke compartment barriers?

A: Fire-rated barriers are not necessarily smoke compartment barriers. They are two distinctly different barriers with different purposes. Now, if an organization wanted to combine the two purposes into one barrier, then that is acceptable as long as you meet the most restrictive requirements of each type of barrier. A fire-rated barrier requires fire-rated opening protectives (i.e., doors and windows). Fire-rated door assemblies are required to have fire-rated doors and frames, self-closing devices, and positive latching. A fire-rated barrier that is rated at two hours or greater must have fire dampers in any HVAC ductwork that penetrates that barrier.

Read the full answer.  

 



September 30, 2015


Topic Area: Safety


Recent Posts

Cleanliness in Hospitals: Clinical Priority and Community Perception

EVS managers and communities value cleanliness for complementary reasons: managers for safety and compliance, communities for trust and comfort.


Dana-Farber Receives $50M Gift for Planned Cancer Hospital

A $50 million grant from the Yawkey Foundation will support construction of Dana-Farber Cancer Institute’s planned 450,000-square-foot cancer hospital.


Clarinda Regional Health Center Reports Data Security Incident

On or around December 15, 2025, Clarinda learned that certain data within its network may have been accessed without authorization.


Gaps in Nurses' Environmental Cleaning Knowledge Grow Amid Rising EVS Pressures

Environmental cleaning is crucial in preventing HAIs, but when the responsibility falls to those outside of EVS teams, problems arise. 


Ground Broken on the Southern Nevada Forensic Facility

Construction on the new secure forensic psychiatric hospital is expected to be completed in 2029.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.