Regulations, Codes & Standards Q&A: Corrective Maintenance Work

Brad Keyes discusses regulations on corrective maintenance work

By Brad Keyes / Special to Healthcare Facilities Today


Q: Thanks for all the great information that you provide; it is very helpful! I just have a quick question about corrective maintenance work orders. Do you know how many days a mechanic has to make repairs when the PM/equipment fails?

A: There are no set standards on how many days a technician may take to resolve a defective piece of equipment. In regards to a survey, CMS does have standards that say no more than 60- days are permitted to resolve deficiencies identified by a surveyor during a survey (an accreditation survey or a CMS validation survey), but that is not quite the same as a routine non- survey fix and repair situation. CMS also says if a particular LSC deficiency requires more than 60-days to resolve (i.e. time to design, competitive bidding, delivery lead-time, availability of space, etc.), then the organization may submit a Time-Limited Waiver request as part of their Plan of Correction to request more than 60-days to resolve an issue.

The expectation is the organization will take appropriate and immediate action to resolve all deficiencies, and when they cannot be resolved the same day they are discovered then an ILSM assessment must be conducted.

Brad Keyes, CHSP, is the owner of KEYES Life Safety Compliance, and his expertise is in the management of the Life Safety Program, including the Environment of Care and Emergency Management programs.



November 4, 2020


Topic Area: Regulations, Codes & Standards


Recent Posts

UMC Health System Grapples with IT Outage from Ransomware Attack

The organization’s facilities remained operational despite the IT outage.


Boston Medical Center Welcomes Two New Facilities into Health System

Good Samaritan Medical Center and St. Elizabeth’s Medical Center are officially part of the health system.


Inspira Health Breaks Ground on Mullica Hill Expansion

The new 150,000-square-foot, five-story wing is expected to be open in the first quarter of 2027.


Cleanology: The Need for a Study of Cleaning

There are no accepted risk-based standards to verify whether a hospital is truly clean and safe.


Hurricane Helene Forces Unicoi County Hospital to Evacuate

A helicopter was called in alongside the Tennessee National Guard to help complete the evacuation.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.