UC San Diego Begins $3 Billion Project on Medical Campus

Campus will go through five phases during development as hospital still operates

By HFT Editorial Staff


Construction began recently on 10 acres on the Hillcrest Campus of UC San Diego for the first phase of a multi-phase plan to redevelop the full medical campus, providing new facilities, new technology, increased capacity, and expanded care offering.

To enable the hospital to operate throughout construction, building a new hospital required a complete redevelopment of the campus through a phased plan. The first phase of redevelopment includes a 250,000-square-foot outpatient pavilion anticipated to open in 2025, which will house specialty clinical programs, including oncology, neurosurgery, orthopedics, ambulatory surgery operating rooms, gastroenterology procedure rooms, advanced imaging, infusion, and radiation oncology.

This phase also includes a 1,850-space parking structure anticipated to open in 2023, which will allow for the demolition of two existing parking structures, consolidating patient and employee parking for improved patient and caregiver access and experience.

Over the next 15 years, construction on the $2.5-$3 billion project will continue on the Hillcrest Campus in five major phases, during which the majority of the existing buildings will be demolished and replaced. These phases were created to reduce impact on the surrounding community while ensuring current, critical campus functions remain operational.

Nearly one-half of the buildings on the Hillcrest Campus were constructed prior to 1970. The redevelopment provides an opportunity to design and build modern, sustainable and efficient medical facilities, but it is also necessary to comply with seismic safety provisions of the California Hospital Code, which ensures that in the event of a major seismic event, essential facilities such as hospitals will continue to operate.



November 11, 2021


Topic Area: Construction


Recent Posts

Gaps in Nurses' Environmental Cleaning Knowledge Grow Amid Rising EVS Pressures

Environmental cleaning is crucial in preventing HAIs, but when the responsibility falls to those outside of EVS teams, problems arise. 


Ground Broken on the Southern Nevada Forensic Facility

Construction on the new secure forensic psychiatric hospital is expected to be completed in 2029.


Jackson Hospital Falls Victim to Third-Party Cybersecurity Incident

Jackson Hospital has no evidence that any personal information has been or will be used for identity theft as a direct result of this incident.


Making Healthcare Lighting Retrofits Work

Effective operational planning determines whether a retrofit project improves a facility or creates new problems.


Stadium Design is Reshaping Healthcare Facilities

Hospitals are turning to the sports industry for innovative ways to support healing and improve the patient experience.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.