Avoiding building envelope commissioning pitfalls

Though building envelope design and construction seems straightforward, these steps can help ensure a successful construction and commissioning process


The building envelope seems so simple. In a traditional design phase, the architect selects a wall and roof system and writes the specification. The general contractor will install what was specified and the warranty will cover the materials installed, provided the installation conforms to the manufacturer’s guidelines.

What could be simpler? But think about it. Between the general contractor, architect, material supplier, and facility management staff, who has the healthcare facility’s long term interest best at heart? That’s right, the facility staff that will have to live with whatever is provided, according to an article from Building Operating Management on the FacilitiesNet website.

The architect, contractor, even the construction manager may not look at the building envelope system the same as the facility staff. The perspective that the facility management team provides is important to the long-term successful use of the new facility. After all, they helped define success during the owner’s project requirements workshop in the pre-design phase.

A simple way to illustrate this point is to consider what is necessary to keep the warranties in place during the operation phase of commissioning. The facility staff will have the opportunity to point out how these restrictions hinder their ability to do their jobs during the owner’s project requirements workshop. And unless the facility staff is made aware of these requirements, the guarantee on the brand new roof could be accidentally voided.

Read the article.



September 17, 2018


Topic Area: Project Management


Recent Posts

Reframing the Construction Manager as a Community Manager

Managers must work with patients, community residents and other interested parties to ensure a smooth, successful construction projects


Health First Celebrates 'Topping Off' Ceremony for New Cape Canaveral Hospital Campus

Construction is slated to finish by the end of 2026 or early 2027.


The University of Hawai'i Cancer Center Caught Up in Cyberattack

Investigations are still ongoing to assess other sensitive information that may have been impacted.


Mature Dry Surface Biofilm Presents a Problem for Candida Auris

Multiple methods are described in the literature, but no consensus has been reached for disinfection efficacy tests against biofilms.


Sutter Health's Arden Care Center Officially Opens

With an adaptive reuse of an underutilized office building, the 70,000 square-foot facility was renovated to meet current healthcare standards.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.