Focus: Facility Design

Banner Boswell Medical Center Project Uses Prefabricated Wall Panels

The panels saved approximately three months of construction time and allowed for enhanced safety precautions


The recent construct project at the Banner Boswell Medical Center  in Sun City, Ariz., involved the use of prefabricated interior and exterior wall panels, constructed offsite and delivered to the job site for installation, according to an article on the AZ Big Media website.

The use of prefabricated wall panels saving approximately three months of construction time and  allowed for enhanced safety precautions during the COVID-19 pandemic.

Of the 625 prefabricated panels used at Banner Boswell, most were fitted to the outside of the new tower as part of the exterior skin. 

Approximately 125 of the prefabricated wall panels were interior partition walls and were placed inside the emergency department.

Many healthcare architects, contractors and owners are shifting their paradigm and increasingly moving towards modular design and prefabrication, according to an article on the Healthcare Construction + Design website. In addition to saving time, the shift is allowing for better building information models. Prefabrication requires architects and consultants to maintain better building information models (BIM) because subcontractor trades need a model to fabricate components.

Read the full AZ Big Media article.

 

 



October 15, 2020


Topic Area: Construction and Design


Recent Posts

Rethinking Carpeting's Role in Senior Care Facilities

New research from the Carpet and Rug Institute finds that carpet supports healthier indoor environments.


Parkview Health Breaks Ground on New Hospital in West Lafayette, IN

The hospital is scheduled to open in June 2028.


Loma Linda University Health Experiences Data Breach via AI Tool

A file containing limited patient information was inadvertently uploaded to an external artificial intelligence (AI) platform.


Inside One of Healthcare's Most Ambitious Hospital Projects 

When someone faces a serious medical condition, having access to world-class care close to home can make all the difference. 


Turning Condensate Loss into a Systemwide Steam Efficiency Opportunity

Case study: How APM Steam helped Atrium Health Cabarrus uncover hidden steam system inefficiencies and build an actionable repair plan with a projected $144,949 in annual energy savings.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.