Case study / Focus: Facility Design

Colorado State University Health and Medical Center Medical Services Building

This project includes Vista stainless and glass railing on spiral staircase and overlooks, and Point-supported glass smoke baffle


Project Information

Location: Fort Collins, Colo.

Architect: Bennett Wagner Grody Architects

GC: Adolphson & Peterson Subcontractor: ISEC-Colorado

Glass Supplier: Glasshape North America L.P.

Completion: June 2017

Scope: This project includes Vista stainless and glass railing on spiral staircase and overlooks, and Point-supported glass smoke baffle. Stairs called for fascia-mounted Vista railing, and overlooks were top mounted. Given the compressed schedule, and complexity of the work, Trex Commercial Products utilized a 3-D laser scanning system to design and produce the railing.

Additional Background:

Colorado State University recently opened the doors to its brand new, state-of-the-art medical center — a $59 million, 113,000-square-foot facility that consolidates the university’s medical offerings into one building for students, faculty, staff and community members.

When the original railing supplier was unable to complete the work just as the project was 90 percent complete – threatening to derail the project and throw off the construction timeline — Trex Commercial Products took over. Given the compressed schedule, and complexity of the work, Trex Commercial Products recommended using a 3-D laser scanning system to design and produce the remaining railing, integrating it seamlessly with the existing work.

Trex Commercial Products used a 3-D scanning tool, known as High Definition Surveying (HDS) or Reality Capture, to produce high- accuracy mapping of the project’s design and geometry.

Two-to-three scans were taken of each floor, and the collected data points were then turned into a “point cloud” file with extremely accurate dimensions.

Working from this, Trex created submittal drawings off of the project scan, eliminating the need for field dimensioning post-architectural approval. In fact, the 3-D scanning proved so effective that there were zero dimensional remakes done on site – saving both time and the cost of fabrication rework.

With Trex expertise, Colorado State University was able to complete the center as planned. The end result, accomplished with 720 combined linear feet of Trex Commercial Products’ Vista stainless steel and glass railing and Point supported smoke baffle, offers abounding views and allows unfiltered light to fill the space.

The circular staircase features a fascia-mounted railing application, whereas a top-mounted installation was chosen for accompanying overlooks. The fascia-mounted system is facilitated by attaching a standard 4”x 6” stainless steel mounting plate to a steel weld block by two drilled-and-tapped holes. 

The block was then welded directly to the stair stringer. The top-mounted Vista railing system has railing posts, along with steel post insert material, embedded into core-drilled holes in the concrete, which are covered by stainless steel escutcheon plates. And what better way to provide a clear view than with ½” monolithic, fully tempered glass.

Now open, CSU’s medical center provides a much-needed central facility for health and well-being, benefitting the entire campus community.

 



October 16, 2018


Topic Area: Project News for Healthcare Facilities


Recent Posts

Respecting EVS Workers: 19 Minutes Is Not Enough

The infection control problem is time, and it's up to facility managers, EVS directors and infection preventionists to address the problem.


Where are the Greenhouse Gas Emissions Hotspots in Healthcare?

First-year findings from Boston Medical Center show medical waste generates a disproportionate amount of healthcare emissions.


Caravel Autism Health Opens Clinic in Lake Zurich, Illinois

The clinic features colorful, sensory-friendly spaces where children work one-on-one with therapists.


The Future of Healthcare Facility Construction Projects

Brian Cowperthwaite highlights the invisible work that impacts everyone who walks through a healthcare facility.


Ground Broken on Jupiter Medical Center's Second Hospital

The 53,000-square-foot hospital will include 29 inpatient beds, four operating rooms, 24-hour emergency services, a diagnostic laboratory and imaging services.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.