Life Safety Q&A: Powering Exit Signs

If batteries are removed from exit signs, do signs still need to be tested?


Question: We had a mock survey at our hospital from an accrediting body. One of the surveyors on the Life Safety team told us that if we removed the batteries from our exit signs that we would no longer have to do the monthly tests on the signs since they are connected to the emergency generator. Everything that I can find insists otherwise but another member of staff insists on having them removed. Is this a valid claim?

Answer from Brad Keyes: No, I do not believe it is. That seems to be a surveyor’s preference, and would violate the manufacturer’s recommendations. You are required to comply with the manufacturer’s recommendations for preventive maintenance frequencies and methods, unless you qualify for a CMS approved Alternative Equipment Management (AEM) program. 

Regardless if the “EXIT” sign has a battery-backup for emergency power or relies on the facility’s generator, you still need to do monthly inspections to ensure the signs are still illuminated. 

Unless you get it in writing from that particular accreditation organization, removing the batteries from a battery-powered “EXIT” would violate the manufacturer’s recommendations and is likely to be cited by some other knowledgeable surveyor. And it would likely not be approved by the CMS surveyors if they conducted a validation survey. 

Brad Keyes, CHSP, is the owner of KEYES Life Safety Compliance, and his expertise is in the management of the Life Safety Program, including the Environment of Care and Emergency Management programs.



December 16, 2020


Topic Area: Safety


Recent Posts

How Efficiency Checklists Help Hospitals Save Energy, Water and Money

Keith Edgerton explains how a simple, systematic tool can help healthcare facilities identify savings, support sustainability goals and reinvest in long-term decarbonization.


Designing with Heart: Seen Health Center Blends Cultural Warmth and Clinical Care

Case study: The Alhambra-based facility uses Wilsonart Woodgrains to create a space where comfort, tradition and durability come together for an elevated senior care experience.


Rutgers Health and University Hospital Breaks Ground on Campus Expansion

The groundbreaking follows the long-awaited demolition of administrative offices built in the 1970s.


What to Consider When Modernizing Healthcare Facilities

While there has been a call to preserve old buildings, healthcare facilities need to weigh the options of patient care.


Corewell Health Beaumont Troy Hospital to Build New Tower

The tower is expected to be completed in 2030.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.