Maryland healthcare organization ramps up pandemic preparedness

The University of Maryland Medical Center scrambled to find ventilators, create surge capacity


Richie Stever, is the director of operations and maintenance at the University of Maryland Medical Center in Baltimore. A whirlwind of activity from his department rapidly expandedCOVID-19-related capacity at the medical center, according to a article from Building Operating Management on the FacilitiesNet website.

Together with the operations team, the hospital created eight different surge plans, with each step up converting more space to make it COVID-19-related. 

In May, at Surge 4, Stever's team had moved the facility from 100 isolation rooms to 300 over five weeks, with the guidance telling them to make as many negative pressure rooms as possible. 

The medical center's original isolation rooms are managed by the building's exhaust system, so to add capacity they removed windows and ducted HEPA units out of them. They created anterooms and airlocks on the fly. They tweaked the HVAC system, turning down supply and turning up return in certain areas. 

Read the article.

 

 



July 14, 2020


Topic Area: Maintenance and Operations


Recent Posts

Cleanliness in Hospitals: Clinical Priority and Community Perception

EVS managers and communities value cleanliness for complementary reasons: managers for safety and compliance, communities for trust and comfort.


Dana-Farber Receives $50M Gift for Planned Cancer Hospital

A $50 million grant from the Yawkey Foundation will support construction of Dana-Farber Cancer Institute’s planned 450,000-square-foot cancer hospital.


Clarinda Regional Health Center Reports Data Security Incident

On or around December 15, 2025, Clarinda learned that certain data within its network may have been accessed without authorization.


Gaps in Nurses' Environmental Cleaning Knowledge Grow Amid Rising EVS Pressures

Environmental cleaning is crucial in preventing HAIs, but when the responsibility falls to those outside of EVS teams, problems arise. 


Ground Broken on the Southern Nevada Forensic Facility

Construction on the new secure forensic psychiatric hospital is expected to be completed in 2029.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.