N.Y. VA facility problems blamed on poor maintenance oversight

Surgeries were suspended between mid-February and early June of 2016 after metal particles were found in the airflow to the operating rooms


The conditions that prompted surgery cancellations at the Northport (N.Y.) VA Medical Center last year arose because of poor oversight of maintenance operations, according to an article on the Newsday website.

A report on internal investigations commissioned by the Department of Veterans Affairs focused on the breakdown of cooling towers and air conditioning units responsible for ventilation in the surgical area at Long Island’s only VA hospital. 

Surgeries were suspended between mid-February and early June of 2016 after metal particles were found in the airflow to the operating rooms.

The reports also conclude that the failings of the engineering department at Northport was a significant drain on financial resources there. For instance, failure to complete maintenance projects in a timely fashion — highlighted in a second report — resulted in the loss of more than $9 million in federal funding.

Read the article.

 



October 12, 2017


Topic Area: HVAC


Recent Posts

Cleanliness in Hospitals: Clinical Priority and Community Perception

EVS managers and communities value cleanliness for complementary reasons: managers for safety and compliance, communities for trust and comfort.


Dana-Farber Receives $50M Gift for Planned Cancer Hospital

A $50 million grant from the Yawkey Foundation will support construction of Dana-Farber Cancer Institute’s planned 450,000-square-foot cancer hospital.


Clarinda Regional Health Center Reports Data Security Incident

On or around December 15, 2025, Clarinda learned that certain data within its network may have been accessed without authorization.


Gaps in Nurses' Environmental Cleaning Knowledge Grow Amid Rising EVS Pressures

Environmental cleaning is crucial in preventing HAIs, but when the responsibility falls to those outside of EVS teams, problems arise. 


Ground Broken on the Southern Nevada Forensic Facility

Construction on the new secure forensic psychiatric hospital is expected to be completed in 2029.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.