Oklahoma VA hospital construction collapse blamed on poor planning

Federal report says repairs will cost $17.5 million


A VA hospital construction collapse in Muskogee, Okla., blamed on poor planning and will cost $17.5 million to repair, according to a article on the News OK website.

The VA's Office of Inspector General found the shoddily planned construction of a generator at Muskogee's Jack C. Montgomery VA Medical Center, which has cost $5 million to date, caused the collapse of a hillside and parking lot.

The report, the result of a 27-month investigation, follows a similar report that found two construction projects at the Oklahoma City VA Medical Center are $10.8 million over budget and several years behind schedule due to shoddy contracting and poor oversight, the article said.

VA investigators found failures occurred along the chain of command. The hospital's chief of engineering should have hired an adviser — formally known as a contracting officer's representative, or COR — with excavating experience, the report said. As investigators wrote, “the COR's decisions throughout the project demonstrated his inexperience managing an excavation.”

Read the article.

 

 



April 9, 2018


Topic Area: Construction


Recent Posts

Grounding Healthcare Spaces in Hospitality Principles

Thoughtful design can establish the calm of a spa and the restorative feeling of a resort in healthcare spaces, bringing benefits for patients and care providers.


UC Davis Health Selects Rudolph and Sletten for Central Utility Plant Expansion

Work is already underway with substantial completion anticipated in the fall of 2027.


Cape Cod Healthcare Opens Upper 2 Floors of Edwin Barbey Patient Care Pavilion

The first two floors opened for patients in May 2025 and house the Davenport-Mugar Cancer Center.


Building Sustainable Healthcare for an Aging Population

Traditional responses — building more primary and secondary care facilities — are no longer sustainable.


Froedtert ThedaCare Announces Opening of ThedaCare Medical Center-Oshkosh

The organization broke ground on the health campus in March 2024.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.