Oklahoma VA hospital construction collapse blamed on poor planning

Federal report says repairs will cost $17.5 million


A VA hospital construction collapse in Muskogee, Okla., blamed on poor planning and will cost $17.5 million to repair, according to a article on the News OK website.

The VA's Office of Inspector General found the shoddily planned construction of a generator at Muskogee's Jack C. Montgomery VA Medical Center, which has cost $5 million to date, caused the collapse of a hillside and parking lot.

The report, the result of a 27-month investigation, follows a similar report that found two construction projects at the Oklahoma City VA Medical Center are $10.8 million over budget and several years behind schedule due to shoddy contracting and poor oversight, the article said.

VA investigators found failures occurred along the chain of command. The hospital's chief of engineering should have hired an adviser — formally known as a contracting officer's representative, or COR — with excavating experience, the report said. As investigators wrote, “the COR's decisions throughout the project demonstrated his inexperience managing an excavation.”

Read the article.

 

 



April 9, 2018


Topic Area: Construction


Recent Posts

Why Healthcare Facilities Management Is Critical to Patient Safety 

Hospitals and other healthcare facilities rely on much more than doctors and nurses to keep patients safe.


Brookdale Senior Living Announces Acquisition of the Brookdale Galleria Community

The 244-unit independent living and assisted living community is located directly adjacent to The Galleria shopping and entertainment complex.


Erlanger Health System Falls Victim to Data Breach

Erlanger has no evidence of any improper use of the information because of this incident.


Technological Readiness: The Missing Construction Milestone

A new building can be complete by most measures but still not be technologically or operationally ready.


From Cooling Towers to Cost Savings: Hospital Seizes Power-Saving Opportunity

Case study: Arkansas hospital increases energy efficiency by diagnosing cooling tower issues and treating its entire mechanical system.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.