Regulations, Codes & Standards Q&A: Cabinets in a corridor, Part 2

Brad Keyes discusses regulations for cabinets in a corridor

By Brad Keyes / Special to Healthcare Facilities Today


Cabinets in a Corridor – Part 2

Q: Is there a codified requirement for doors in a cabinet mounted in a hospital egress corridor? We have worked on projects when a nurse server; i.e., pass through cabinet, was required by the local AHJ to have positive latching on the cabinet door in order to protect the sanctity of the egress corridor. But when it is just a typical cabinet (non-pass through), is there a danger to the egress corridor if the cabinet doors do not have positive latching?

A: The only code requirements that I can think of are corridor obstruction and projection. A nurse server that has an open pass-through to the patient room from the corridor is required to have a door that meets the requirements of 19.3.6.3 of the 2012 LSC for corridor doors, such as positive latching, 1¾-inch thick solid-bonded wood core, and resisting the passage of smoke, because it needs to separate the corridor from the patient room. I think a typical cabinet that does not have a pass-though would not have to have a door that is positive latching because positive latching is only required when the door is separating a corridor from a room. If there is no pass-through, then there is no need for a positive latching door.   

Brad Keyes, CHSP, is the owner of KEYES Life Safety Compliance, and his expertise is in the management of the Life Safety Program, including the Environment of Care and Emergency Management programs.

 

 



April 11, 2018


Topic Area: Regulations, Codes & Standards


Recent Posts

Cleanliness in Hospitals: Clinical Priority and Community Perception

EVS managers and communities value cleanliness for complementary reasons: managers for safety and compliance, communities for trust and comfort.


Dana-Farber Receives $50M Gift for Planned Cancer Hospital

A $50 million grant from the Yawkey Foundation will support construction of Dana-Farber Cancer Institute’s planned 450,000-square-foot cancer hospital.


Clarinda Regional Health Center Reports Data Security Incident

On or around December 15, 2025, Clarinda learned that certain data within its network may have been accessed without authorization.


Gaps in Nurses' Environmental Cleaning Knowledge Grow Amid Rising EVS Pressures

Environmental cleaning is crucial in preventing HAIs, but when the responsibility falls to those outside of EVS teams, problems arise. 


Ground Broken on the Southern Nevada Forensic Facility

Construction on the new secure forensic psychiatric hospital is expected to be completed in 2029.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.