Focus: Fire-Life Safety / Column

Regulations, Codes & Standards Q&A: Portable fire extinguishers

Brad Keyes discusses regulations for portable fire extinguishers

By Brad Keyes / Special to Healthcare Facilities Today


Q: In regards to portable fire extinguishers, I have a fully sprinkled building but my room that my hot water heaters are in are on the outside of the building. My furthest hot water room is more than 75 feet from the closet fire extinguisher. I looked in the Life Safety Code and have not found any reference on this. Do I need to place a fire extinguisher in this room?

A: Yes, you do… Section 9.7.4.1 of the 2012 LSC requires compliance with NFPA 10. According to chapter 6 of NFPA 10-2010, the installation of portable fire extinguishers is based on the classification of the extinguisher, the capacity of the extinguisher, and the level of hazard the extinguisher is expected to address.

For Class A extinguishers, the maximum travel distance to an extinguisher is 75 feet. For Class B extinguishers, the maximum travel distance is either 30 feet or 50 feet, depending on the capacity of the extinguisher and the expected level of hazard. For Class C extinguishers, the fire is started by electrical current, but the material that burns is either a Class A material or a Class B material, so you space the extinguishers on the class A or Class B requirements. For a Class K extinguisher, the maximum travel distance is 30 feet.  

You need to install an extinguisher to be within the maximum travel distance limits.

Brad Keyes, CHSP, is the owner of KEYES Life Safety Compliance, and his expertise is in the management of the Life Safety Program, including the Environment of Care and Emergency Management programs.

 

 



October 24, 2018


Topic Area: Regulations, Codes & Standards


Recent Posts

Grounding Healthcare Spaces in Hospitality Principles

Thoughtful design can establish the calm of a spa and the restorative feeling of a resort in healthcare spaces, bringing benefits for patients and care providers.


UC Davis Health Selects Rudolph and Sletten for Central Utility Plant Expansion

Work is already underway with substantial completion anticipated in the fall of 2027.


Cape Cod Healthcare Opens Upper 2 Floors of Edwin Barbey Patient Care Pavilion

The first two floors opened for patients in May 2025 and house the Davenport-Mugar Cancer Center.


Building Sustainable Healthcare for an Aging Population

Traditional responses — building more primary and secondary care facilities — are no longer sustainable.


Froedtert ThedaCare Announces Opening of ThedaCare Medical Center-Oshkosh

The organization broke ground on the health campus in March 2024.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.