A big issue in healthcare reconstruction is balancing the construction work with the hospital’s need to maintain 24/7 operations, according to an article on the Building Design & Construction website.
A recent renovation project at Inova Health System’s Fair Oaks (Va.) Hospital tested a reusable infection-control barrier that minimized the effort required to assemble and disassemble the barrier walls.
The new barrier system was specified for several hundred linear feet of infection-control partitions that needed to be built and disassembled during several phases.
The Edge Guard was a great solution because it could be assembled and disassembled by virtually any project team member using just a ladder, and without generating dust.
Grounding Healthcare Spaces in Hospitality Principles
UC Davis Health Selects Rudolph and Sletten for Central Utility Plant Expansion
Cape Cod Healthcare Opens Upper 2 Floors of Edwin Barbey Patient Care Pavilion
Building Sustainable Healthcare for an Aging Population
Froedtert ThedaCare Announces Opening of ThedaCare Medical Center-Oshkosh