Containing Infection Risk During Hospital Construction

Early discussion and risk assessment associated are key to minimizing the potential impact


With a phased build project, hospital administrators, infection preventionists, and other staff must deal with the threat that the construction could spread contaminants, according to an article on the Infection Control Today website.

 Early discussion and risk assessment are key to minimizing the potential impact.

Renovation or construction that happens in preexisting spaces or occupied areas have very different sets of challenges than the building of new facilities. 

The current phase of the construction and the assessment of risk will help determine what is needed. Demolition, for example, in the existing or adjacent areas creates dust and debris. It also creates a need to remove construction debris from the site to an appropriate disposal location. 

According to recent research, some construction companies are not providing adequate training to their workers and subcontractors on how to avoid creating conditions  in healthcare project job sites that could be dangerous to  patients, according to a Construction Dive article

Read the full Infection Control Today article.

 



November 9, 2020


Topic Area: Infection Control


Recent Posts

Preparing Healthcare Facilities for Severe Thunderstorms

Hardening plans and collaboration with local stakeholders can aid in prep for severe weather.


NLCS Strengthens Safety and Compliance with Comprehensive Electrical Program

Case study: A renewed partnership with Siemens helps the senior living provider meet NFPA 70B standards, reduce risk, and enhance reliability across its communities.


University of South Carolina Opens New Brain Health Center

The center is aimed at expanding access to specialized care for patients with cognitive conditions.


Infrastructure Issues: Assisting Mobility-Challenged Visitors

Parking constraints, mobility needs and patient experience priorities are elevating arrival pathways as a strategic planning issue.


Willis-Knighton Medical Center Upgrades Chilled Water Plant

The medical center sought upgrades through Trane to add capacity, control comfort, increase redundancy and reduce energy costs.


 
 


FREE Newsletter Signup Form

News & Updates | Webcast Alerts
Building Technologies | & More!

 
 
 


All fields are required. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

 
 
 
 

Healthcare Facilities Today membership includes free email newsletters from our facility-industry brands.

Facebook   Twitter   LinkedIn   Posts

Copyright © 2023 TradePress. All rights reserved.